Aqua — Work is underway to install the formwork for the floor slab of the 19th construction (18th hotel) floor. On the 11th (10th) floor, the wall masonry with…
Construction progress, complex updates and real estate investment news from Batumi
Aqua — Work is underway to install the formwork for the floor slab of the 19th construction (18th hotel) floor. On the 11th (10th) floor, the wall masonry with…
Ceramic block masonry walls are being laid on the 5th hotel (4 residential) and 6th (5) floors.
Family Club — Installation of the formwork for the 3rd floor slab continues in Block A. Excavation is underway in Block B.
Block A: in the first half the formwork for the floor slab of the 3rd floor is being erected, in the second half the formwork for the floor slab above the 3rd…
Aqua — Work continues on the installation of formwork for the floor slab of the 19th construction (18th hotel) floor. On 11 (10) the walls are being laid with…
Family Club — In Block A, work is underway to install the formwork for the floor slab of the 3rd floor. Excavation is underway in Block B.
Works on installation of formwork for the floor slab of the 3rd floor continue in Block A. Excavation works are being carried out in Block B. In Block E…
Aqua — Installation of the floor slab formwork on the 19th construction (18th hotel) floor has started. Ceramic block walls are being laid on the 9th (8) and…
Ceramic block wall masonry continues on the 5th construction (4 residential) and 6th (5) floors.
Ceramic block walls are being laid on floors 5 (4) and 6 (5). Building materials are being loaded on the floors.
Family Club — In Block A, the installation of formwork for the 3rd floor floor slab continues and backfilling of the excavation slots is in progress. Excavation…
In Block A, work continues on the formwork for the floor slab on the 3rd floor. Installation of lighting on the floors has started. Excavation works are being…
Aqua — After concreting the columns of the 19th construction (18th hotel) floor, the formwork is dismantled and reinforcement continues. On the 9th (8) and 11th…
Ceramic block wall masonry continues on the 5th construction (4 residential) and 6th (5) floors.
Family Club — Block A: installation of formwork for the floor slab of the 3rd floor Block B: excavation.
Riviera — Installation of the formwork of the floor slab of the 3rd floor continues in Block A. Earthworks are going on in Block B. And in Block E preparations…
Aqua — Concreting of the columns of the 19th construction (18th hotel) floor has been completed. Wall masonry with ceramic block continues on the 9th (8) floor…
Ceramic block masonry walls are being laid on the 5th construction (4 residential) and 6th (5) floors.
In Block A, work is underway to install the formwork for the 3rd floor floor slab and backfill the excavation slots. Excavation of the excavation continues in…
Block A: installation of floor slab formwork for the 3rd floor continues. Block B: excavation works are in progress. Block E: preparation for ceramic block…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st