After concreting on the 19th construction (18th hotel) floor, the vertical structures have been marked and reinforcement has been started. On the 11th (10) and…
Construction progress, complex updates and real estate investment news from Batumi
After concreting on the 19th construction (18th hotel) floor, the vertical structures have been marked and reinforcement has been started. On the 11th (10) and…
On the 5th construction (4 residential), 6th (5) and 7th (6) floors, the laying of walls with ceramic block continues. Loading of construction materials on the…
Family Club — Block A: reinforcement of the floor slab of the 3rd floor is in progress Block B: excavation is in progress.
— In Block A, reinforcement of the floor slab of the 3rd floor continues in the first half and concreting of the floor slab of the 3rd floor is carried out in…
Aqua — Concreting of the floor slab has been carried out on the 19th construction (18 hotel) floor. On 12 (11) and 11 (10) the walls are being masoned with…
Ceramic block masonry walls are being laid on the 5th building (4 residential) as well as on the 6th (5) and 7th (6) floors.
Reinforcement of the floor slab continues on the 3rd floor of Block A. Excavation is underway in Block B.
Aqua — Reinforcement of the floor slab has been completed on the 19th construction floor (18 hotel floors). On 11 (10) and 12 (11) the walls are being laid with…
Riviera — In the 1st half of Block A, reinforcement of the floor slab of the 3rd floor has been completed. Excavation works continue in block B. In block E…
On the 5 hotel (4 residential) and 6 (5) floors the walls are masoned with ceramic block.
Family Club — Reinforcement of the floor slab of the 3rd floor in Block A is underway. Excavation of Block B is underway.
Block A - reinforcement of the floor slab of the 3rd floor started in the first half. Block B - excavation works continue. Block E - ceramic block parapet is…
Aqua — On the 19th construction (18 hotel) floor, reinforcement of the floor slab continues. On the 11th (10), the walls are being laid with ceramic block.
Ceramic block walls are being laid on the 5th construction (4 residential) and 6th (5) floors.
Family Club — Block A Installation of formwork for the 3rd floor floor slab is completed, reinforcement is in progress. Block B Excavation works are in…
Block A In the 1st half works on installation of formwork of the floor slab of the 3rd floor are in progress, in the 2nd half reinforcement of the floor slab of…
Aqua — Installation of the floor slab formwork for the 19th construction (18th hotel) floor has been completed. Reinforcement of the slab has been started. Wall…
On the 5th construction (4 residential) and 6th (5) floors, the walls are being masoned with ceramic block.
Family Club — Installation of the formwork for the 3rd floor slab is underway in Block A. Excavation continues in Block B.
In the 1st half of Block A, the formwork for the 3rd floor floor slab is being erected. In block B, excavation works continue. In block E the ceramic block is…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st