On the 1st floor of block A the concreting of columns took place.
Construction progress, complex updates and real estate investment news from Batumi
On the 1st floor of block A the concreting of columns took place.
Riviera — Column reinforcement continues on the 1st floor of Block A and on the 3rd floor of Block E. The reinforcement of the staircase in block E is also…
Aqua — Work is underway to install the formwork for the floor slab of the 16th construction (15th hotel) floor. On the 6th (5th) floor the walls are being laid…
Aqua — Work is underway to install the formwork for the floor slab of the 16th construction (15th hotel) floor. On the 6th (5th) floor the walls are being…
Reinforcement of the floor slab above the 7th construction (6th residential) floor is completed. Laying of ceramic block walls on the 2nd (1st) floor is in…
Column formwork is being assembled on the 1st floor of Block A.
Riviera — Column reinforcement continues on the 1st floor of Block A and on the 3rd floor of Block E.
Riviera — Block A: on the 1st floor the reinforcement of columns is being carried out. Block E: staircase formwork is being installed, column reinforcement…
In Block A, reinforcement and installation of column formwork is in progress.
Elite Family Residence — Reinforcement of the floor slab above the 7th construction (6 hotel) floor continues. The masonry walls are going up on the 2nd(1st)…
Aqua — The installation of formwork for the floor slab of the 16th construction (15th hotel) floor has started. Ceramic block masonry walls started on the 6th…
Reinforcement of the floor slab above the 7th construction (6 residential) floor is in progress. Wall masonry is underway on the 2nd(1) floor.
In Block A, reinforcement and formwork installation of the 1st floor columns is in progress.
Riviera — Reinforcement of the 1st floor columns is underway in Block A. Reinforcement of the 3rd floor columns is underway in Block E. Staircase formwork is…
Aqua — On the 15th construction (14 hotel) floor, the column formwork is being dismantled. On the 5th (4) floor, the masonry of the walls with ceramic block…
Due to safety rules, no outdoor work is being carried out. Inside the construction sites, masonry walls are being laid and cleaned.
In Block A, reinforcement of the 1st floor columns and installation of column formwork continues.
Riviera — Reinforcement of the 1st floor columns in Block A. Reinforcement of the 3rd floor columns and staircase reinforcement in Block E is in progress.
Reinforcement of the pavement slab above the 7th construction (6th residential) floor is in progress.
Aqua — On the 15th construction (14 hotel) floor the concreting of columns has taken place. On the 5th (4) floor the block masonry is in progress.
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st