Construction progress, complex updates and real estate investment news from Batumi

Projects 1 min read
25.09.2023 — Elite Family Residence

On the 7th construction (6 residential) floor the dismantling of the column formwork after concreting is in progress. On the 2(1) storey, the masonry walls…

Wyndham Grand Batumi Gonio Editorial

Projects 1 min read
25.09.2023 — Wyndham Grand Residences Batumi Gonio.

Riviera — In Block A, reinforcement of the 1st floor columns is being carried out. In Block E - installation of staircase formwork and reinforcement of the 3rd…

Wyndham Grand Batumi Gonio Editorial

Projects 1 min read
25.09.2023 — Wyndham Grand Residences Batumi Gonio.

Aqua — Concreting of the floor slab has been carried out on the 15th construction (14 hotel) floor. Wall masonry with ceramic block continues on the 5th (4)…

Wyndham Grand Batumi Gonio Editorial

Projects 1 min read
24.09.2023 — Elite Family Residence

Concreting of the vertical structure took place on the 7th construction (6th residential) floor.

Wyndham Grand Batumi Gonio Editorial

Projects 1 min read
24.09.2023 — Wyndham Grand Residences Batumi Gonio.

Riviera — In Block A, reinforcement of the 1st floor columns is in progress. In Block E, reinforcement of the 3rd floor columns and installation of staircase…

Wyndham Grand Batumi Gonio Editorial

Projects 1 min read
23.09.2023 — Elite Family Residence

On the 7th construction (6th residential) floor the reinforcement of columns is carried out. On the 2(1) floor - laying of walls with ceramic block.

Wyndham Grand Batumi Gonio Editorial

Projects 1 min read
23.09.2023 – Wyndham Grand Residences Batumi Gonio.

Riviera – In Block A, reinforcement of the 1st floor columns is in progress. In block E - reinforcement of columns of the 3rd floor, as well as installation of…

Wyndham Grand Batumi Gonio Editorial

Projects 1 min read
23.09.2023 — Wyndham Grand Residences Batumi Gonio.

Aqua — Reinforcement of the floor slab of the 15th construction (14th hotel) floor is in progress. Block wall masonry is being done on the 5th (4) floor.

Wyndham Grand Batumi Gonio Editorial

Projects 1 min read
22.09.2023 — Elite Family Residence

Reinforcement of vertical structures continues on the 7th (6th residential) floor. Ceramic block walls are being laid on 2(1).

Wyndham Grand Batumi Gonio Editorial

Projects 1 min read
22.09.2023 — Wyndham Grand Residences Batumi Gonio.

Riviera — Concreting of the 1st floor slab has taken place in Block A. In Block E, welding and locksmithing works for the installation of the staircase formwork…

Wyndham Grand Batumi Gonio Editorial

Projects 1 min read
22.09.2023 — Wyndham Grand Residences Batumi Gonio.

Aqua — Reinforcement of the floor slab continues on the 15th construction (14 hotel) floor. On 4(3) and 5 (4) the walls are being laid with ceramic block.

Wyndham Grand Batumi Gonio Editorial

Projects 1 min read
21.09.2023 —

Elite Family Residence — On the 7th construction (6th residential) floor the reinforcement of columns is taking place. On the 2(1) floor, the walls are being…

Wyndham Grand Batumi Gonio Editorial

Projects 1 min read
21.09.2023 — Wyndham Grand Residences Batumi Gonio.

Riviera — Reinforcement of the floor slab continues on the 1st floor of Block A. On the 3rd floor of Block E, reinforcement of columns is underway, and…

Wyndham Grand Batumi Gonio Editorial

Projects 1 min read
21.09.2023 — Wyndham Grand Residences Batumi Gonio.

Aqua — Reinforcement of the floor slab of the 15th construction (14th hotel) floor is in progress. On floors 4(3) and 5(4) the walls are being laid with ceramic…

Wyndham Grand Batumi Gonio Editorial

Projects 1 min read
20.09.2023 — Elite Family Residence

Reinforcement of vertical structures is underway on the 7th construction (6th residential) floor. Wall masonry work continues on the 2nd(1) floor.

Wyndham Grand Batumi Gonio Editorial

Projects 1 min read
20.09.2023 - Wyndham Grand Residences Batumi Gonio.

Aqua - Installation of the floor slab formwork is underway on the 15th construction (14 hotel) floor. On the 4th (3) and 5th (4) floors, masonry walls continue…

Wyndham Grand Batumi Gonio Editorial

Projects 1 min read
19.09.2023 - Elite Family Residence

Column reinforcement continues on the 7th construction (6th residential) floor. Block wall masonry is in progress on the 2nd (1st) floor.

Wyndham Grand Batumi Gonio Editorial

Projects of the complex

Hover a card to see the figures

Гонио, Батуми Aqua
Aqua
With fixed income
10% per year
Without fixed income
up to 15% per year
Price per m²
9 478 € / м2
Request an offer
Гонио, Батуми Family Club
Family Club
With fixed income
10% per year
Without fixed income
up to 13% per year
Price per m²
9 080 € / м2
Request an offer
Гонио, Батуми Riviera
Riviera
With fixed income
11% per year
Without fixed income
up to 14% per year
Price per m²
6 471 € / м2
Request an offer
Гонио, Батуми Villas
Villas
With fixed income
11% per year
Without fixed income
up to 14% per year
Price per m²
5 808 € / м2
Request an offer
Гонио, Батуми Sky Castle
Sky Castle
Request an offer

Fixed income is set out in the agreement with the European Village holding.