Waterproofing of the underground part of the foundation is in progress.
Construction progress, complex updates and real estate investment news from Batumi
Waterproofing of the underground part of the foundation is in progress.
Riviera - Concreting of the 1st floor columns has been completed in Block A. Reinforcement of the floor slab is in progress. Staircase formwork is being…
Aqua - On the 15th construction (14 hotel) floor, work continues on the installation of formwork for the floor slab. In parallel, on the 5th (4) and 4th (3)…
Ceramic block walls continue to be laid on the 2nd construction (1 residential) floor.
Riviera - Concreting of the floor slab of the 3rd floor has been carried out in Block E, as well as staircase formwork installation works have been continued…
Aqua - On the 15th construction (14 hotel) floor the floor slab formwork is being installed. Wall masonry continues on floors 4(3) and 5(4).
Aqua - Work has started on the floor slab formwork on the 15th construction (14th hotel) floor. Wall masonry continues on floors 4 (3) and 5 (4).
On the 2nd building (1 residential), the masonry of walls with ceramic block continues. Reinforcement of vertical structures is in progress on Building 7 (6…
Waterproofing of the underground part of the foundation is in progress.
Riviera - Reinforcement of the 1st floor slab is underway in Block A. Staircase formwork installation is underway in Block E.
Reinforcement of vertical structures continues on the 7th construction (6th residential) floor. Ceramic block masonry walls are being laid on the 2nd(1) floor.
Work on waterproofing of the underground part of the foundation is in progress.
Riviera - Block A: reinforcement of the 1st floor floor slab Block E: installation of staircase formwork.
Aqua - On the 14th construction (13 hotel) floor after concreting the columns dismantled formwork. On the 4th (3) and 5th (4) floors, work continues on masonry…
Reinforcement of vertical structures is underway on the 7th construction (6th residential) floor. On the 2nd (1) floor, the masonry walls continue to be built.
Waterproofing of the underground part of the foundation was carried out.
Riviera - Reinforcement of the floor slab continues on the 1st floor of Block A. The staircase formwork is being installed in block E.
Aqua - Concreting of columns has taken place on the 14th construction (13 hotel) floor. On the 5th (4) floor the block walling has started, on the 3rd (2) and…
Aqua - On the 14th construction floor (13th hotel floor) the installation of column formwork has started. Ceramic block walling continues on floors 3(2) and…
Riviera - Reinforcement of the floor slab of the 1st floor continues in block A. In Block E, installation of staircase formwork.
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st