On the 7th construction (6th residential) floor the reinforcement of columns is underway. On the 2nd (1) floor ceramic block walling is in progress.
Construction progress, complex updates and real estate investment news from Batumi
On the 7th construction (6th residential) floor the reinforcement of columns is underway. On the 2nd (1) floor ceramic block walling is in progress.
Reinforcement of vertical structures continues on the 7th construction (6th residential) floor. Ceramic block wall masonry is underway on the 2nd (1) floor…
Riviera - Reinforcement of the 1st floor slab continues in Block A. In Block E the staircase formwork is being installed and preparation for concreting of the…
Aqua - Reinforcement of columns on the 14th construction floor (13th hotel floor) and installation of fence posts is in progress. On 3 (2) and 4 (3) the laying…
Reinforcement of vertical structures continues on the 7th construction (6th residential) floor. On the 2nd (1) floor, the walls are being laid with ceramic…
Riviera - Block A: reinforcement of the floor slab of the 1st floor. Block E: installation of staircase formwork and reinforcement of the 3rd floor slab
Aqua - Reinforcement of columns and installation of safety posts is underway on the 14th construction (13 hotel) floor. On the 3(2) and 4(3) floors, block…
Aqua - Reinforcement of columns and installation of safety posts is underway on the 14th construction (13 hotel) floor. On the 3(2) and 4(3) floors, block…
Reinforcement of vertical structures on the 7th construction (6th residential) floor has started.
Riviera - Reinforcement of the 1st floor slab continues in Block A. Staircase formwork installation and reinforcement of the 3rd floor slab is underway in Block…
Aqua - On the 14th construction (13th hotel) floor the reinforcement of columns and installation of security pillars is in progress. On the 3(2) and 4(3)…
Geodetic bifurcation works on the 7th construction (6th residential) floor.
Aqua - Concreting of the floor slab of the 14th construction (13th hotel) floor. On 3(2) and 4(3) the walls are being laid with ceramic block.
Riviera - Block E: installation of staircase formwork, reinforcement of the floor slab of the 3rd floor. Block A: reinforcement of the 1st floor slab.
Concreting of the floor slab of the 7th construction (6 residential) floor.Block masonry on the 2nd floor.
Aqua - Reinforcement of the floor slab of the 14th construction (13th hotel) floor is in progress. 3(2) and 4(3) walls are being laid with ceramic block.
Reinforcement of the floor slab of the 1st floor of Block A is under construction.
Riviera - Reinforcement of the floor slab of the 1st floor is going on in block A. In block E - reinforcement of the floor slab of the 3rd floor and…
Aqua Reinforcement of the floor slab of the 14th construction (13th hotel) floor is in progress. On 3(2) and 4(3) walls are being laid with ceramic block.
Family Club Block A: The reinforcement of the slab is going on the 1st floor.
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st