Villas — Villas 3 and 5: reinforcement of the floor slab. Villas 6, 9 and 10: perimeter base planning. Villas 11 and 13: installation of sewerage system below…
Construction progress, complex updates and real estate investment news from Batumi
Villas — Villas 3 and 5: reinforcement of the floor slab. Villas 6, 9 and 10: perimeter base planning. Villas 11 and 13: installation of sewerage system below…
Riviera — The site is in the process of installing security fences on all blocks. In Block C - laying of ceramic block (ground floor) and pouring of the…
Family Club — In Building A, height marking of openings for stained-glass windows, dismantling of staircase formwork (duplexes). In Building B - ceramic block…
Facade, monolithic and sanitary works, installation of metal balcony railings, concreting of the retaining wall footings are in progress. On the fifth floor…
Aqua — Installation of stained glass windows continues at the site. Installation of formwork, framing of balconies with reinforced concrete edges, installation…
Villas — Villas 1 and 4: 3. Installation of staircases and formwork for four columns. Villas 3-5: reinforcement of the floor slab. Villas 11 and 13: backfilling…
Family Club — In Building A, the height marking of openings for curbs and dismantling of staircase formwork (duplexes) is in progress. In Building B - laying of…
Riviera — The site is in the process of installing safety fences on all blocks. In Block C - laying of ceramic block (parapet, roof, ground floor) and…
The following works are carried out: - Material lifting - Terrace screeding - Facade works - Installation of metal fences - Installation of plasterboard…
Villas — - Reinforcement of the floor slab in villa 3 - Reinforcement of the floor slab in villa 5 - Insulation of the foundation in villa 13 - Formwork of the…
Family Club — Block A - Elevation marking of openings for curbs Block B - Ceramoblock masonry on the 1st floor - Reinforcement of vertical structures
Riviera — Block B - Ceramoblock masonry on the 2nd floor - Fireplace masonry - Installation of formwork on the terrace - Ceramoblock masonry on the 3rd floor…
On the 2nd floor: - Installation of GKL partitions On the 3rd floor: - Installation of plumbing in mockup On the 13th floor: - Colouring of balconies in mockup…
The walls are being finished, roof screeding and waterproofing of the fire tank are in progress. Facade works and installation of metal fences are in progress…
Villas — Column formwork is being erected on Villas 4 and 1. The floor slab formwork is being installed on villas 3 and 5. Installation of the formwork for the…
Block A On the 1st floor the masonry of the balconies with ceramic block continues. The height marking of the openings is being made for the curbs. Construction…
Block A Plastering of ventilation duct shafts is in progress. Block B On the 2nd floor walls are being laid with ceramic block and fireplaces are being laid…
Installation of formwork and framing of reinforced concrete sides of balconies continues on the floors. Works on installation of GKL partition walls on the 2nd…
Wall finishing works are being carried out. Installation of plasterboard partitions is in progress. Plumbing, roofing and monolithic works are in progress.
Column formwork is being assembled on Villas 1 and 4. Formwork of the floor slab is being assembled on villas 3 and 5. Insulation of the foundation walls from…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st