The following works are carried out at the object: 1. Laying of porcelain stoneware, units on the 1st residential floor Leveling of the surface and laying of…
Construction progress, complex updates and real estate investment news from Batumi
The following works are carried out at the object: 1. Laying of porcelain stoneware, units on the 1st residential floor Leveling of the surface and laying of…
The following key milestones are being accomplished during construction activities in Blocks A, B and C: 1. Block A, Block B, Block C. Ceramoblock masonry…
Due to unfavorable weather conditions, no construction work is being done at the site today.
Building A 1. Stained Glass Curbs, 2nd Floor The curb installation starts with marking, after which the formwork is set, concrete is poured and compacted. Once…
1. Installation of stained glass structures, 4-5 floors Preparation of openings, installation of durable, environmentally resistant frames. 2. Installation of…
The following works are carried out on site: 1. Facade finishing. Installation of decorative elements and final painting to create an aesthetic and protected…
The following key milestones are being accomplished during construction activities in Blocks A, B and C: 1. Block A, Block B, Block C. Ceramoblock masonry…
The following works are carried out on site: 1. Dismantling of the formwork of the growth chamber and foundation walls Careful removal of temporary structures…
The following works are carried out on site: Building A 1. Plastering of roof parapets Includes application of several layers of plaster to provide durability…
1. Installation of stained glass structures, 4-5 floors Preparation of openings, installation of durable and environmentally resistant frames. 2. Installation…
The following works are carried out at the object: 1. Plastering works, on the 6th floor. Plastering of walls is carried out, taking into account evenness and…
The following key milestones are being accomplished during construction activities in Blocks A, B and C: 1. Block A, Block B, Block C. Ceramoblock masonry…
Due to unfavorable weather conditions, no construction work is being done at the site today.
The following works are carried out at the object: 1. Plastering of 5-6 floors and puttying of the 1st floor. On the 5-6 floors plastering of walls is carried…
The following works are being carried out at the site: 1. Villa 11, 13. Waterproofing of the floor slab. Application of waterproofing material. Followed by…
The following works are carried out at the object: 1. Plastering of openings and preparation for installation of stained-glass windows waterproofing and vapor…
The following works are carried out at the object: Building A 1. Arrangement of curbs for stained glass windows, 1st floor. Laying of curbs that meet the…
The following key milestones are being accomplished during construction activities in Blocks A, B and C: 1. Block B. Pouring of the monolithic sidewalls for the…
Preparation of staircase steps for marble cladding is in progress. Decorative elements on the eastern façade, decorative coating, finishing of terraces…
Villas — Dismantling of foundation wall formwork and strip footings is in progress. Villa 2: installation of column formwork. Villa 6: installation of…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st