Family Club — Block A On the 1st floor the masonry of balconies with ceramic block is in progress. The height marking of the openings is being made for the…
Construction progress, complex updates and real estate investment news from Batumi
Family Club — Block A On the 1st floor the masonry of balconies with ceramic block is in progress. The height marking of the openings is being made for the…
Rivera — Block B On the 2nd floor, ceramic block walls and fireplaces continue to be laid. The underlayment of the supporting sides for the stained glass…
On the 2nd floor, installation of GKL partition walls continues. On the 3rd floor the installation of plumbing in mockup is in progress. On the 13th floor the…
The walls are being finished, the plasterboard framework of internal partitions is being installed, and plumbing works are in progress.
Monolithic works at the site are not being carried out due to heavy rains.
Family Club — Block A On the 1st floor the masonry of balconies with ceramic block is in progress. The height marking of the openings is in progress for the…
Rivera — Block B On the 2nd and 3rd floors the walls are being laid with ceramic block. Fireplaces are being laid, stained-glass windows support sides are being…
Aqua — On the 2nd floor, installation of GKL partitions is in progress. On the 3rd floor - installation of plumbing in mockup. On the 13th floor - painting of…
Finishing of walls, installation of tiles and plasterboard framework of internal partitions, as well as plumbing works are in progress.
Due to heavy rains, no work was carried out at the site.
In block A there is ceramic block laying (1st floor) and height marking of the openings for curbs. In block B - ceramic block masonry (1st and 3rd floor)…
In Block A, the staircases were poured. In Block B - laying of ceramic block (2nd and 3rd floor), laying of fireplaces, lining of stained-glass windows support…
Aqua — Installation of stained glass windows continues at the site. Formwork installation, framing of balconies with reinforced concrete edges, installation of…
Villas — Trenching for the gas pipe continues on site. Villas 1, 2 and 4: installation of reinforced column frame. Villa 3: installation of floor slab formwork…
Facade and roofing works, installation of metal fences and plasterboard framework of internal partitions, wall finishing, tiling, screeding of terraces…
Family Club — In Block A, ceramic block laying continues on the ground floor. In Block B - ceramic block laying on the first and third floors, reinforcement of…
Riviera — Formwork for staircases between the floors is being installed at the site. In Block A, the monolith on the parapet is being poured and the ventilation…
Aqua — Balcony framing with reinforced concrete edges, balcony waterproofing, installation of decorative boxes, dusting of ceilings, construction of lift…
Villas — Dismantling of formwork and construction of fence foundation walls continues on site. Villas 3 and 5: construction of columns. Villas 6-9: primer…
Facade and roofing works, installation of metal fencing, wall finishing, tiling and preparation of the floor for waterproofing in the western fire tank continue…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st