Electrical, facade, roofing and plumbing works, installation of metal fences, installation of plasterboard framework of internal partitions are in progress…
Construction progress, complex updates and real estate investment news from Batumi
Electrical, facade, roofing and plumbing works, installation of metal fences, installation of plasterboard framework of internal partitions are in progress…
Riviera — In Block A, formwork installation on the terrace, formwork installation on the parapet and monolith pouring on the parapet. In Block B - ceramic block…
Family Club — Ceramic block walls continue to be laid on the site - on the fifth floor in Block A and on the third floor in Block B.
Aqua — Balcony framing with reinforced concrete edges, balcony waterproofing, installation of plasterboard framework of internal partitions, installation of…
Villas — Villas 1, 4: backfill around the perimeter of the foundation. Villas 2, 10: insulation of the foundation. Villas 8-9: reinforcement of the floor slab…
Electrical, facade, roofing and plumbing works, installation of metal fences, installation of plasterboard framework of internal partitions are in progress…
Riviera — In Block A, formwork installation on the terrace, formwork installation on the parapet and monolith pouring on the parapet. In Block B - ceramic block…
Aqua — Balcony framing with reinforced concrete edges, balcony waterproofing, installation of plasterboard framework of internal partitions, installation of…
Trenching for the external sewerage system is in progress. Electrical installation works, installation of metal fences, installation of plasterboard framework…
Family Club — Ceramic block walls continue to be laid on the site - on the fifth floor in Block A and on the third floor in Block B.
Riviera — In Block A, fireplaces are being laid and formwork is being installed on the terrace. In Block B - pouring of monolith on the parapet, laying of…
Villas — Villas 1, 2, 4: insulation of the foundation plinth. Villas 6-7: reinforcement of floor slabs. Villas 8-9: waterproofing of joints (laying polystyrene…
Aqua — Framing of balconies with reinforced concrete edges, waterproofing of balconies, installation of plasterboard framework of internal partitions…
Trenching for the external sewerage system is in progress. Electrical installation works, installation of metal fences, installation of plasterboard framework…
Family Club — Ceramic block walls continue to be laid on the site - on the fifth floor in Block A and on the third floor in Block B.
Riviera — In Block A, fireplaces are being laid, formwork is being installed on the terrace and the monolith of the staircases is being poured. In Block B…
Villas — Villas 10-14: foundation planning, compaction of the foundation with a roller, insulation of the foundation. Villas 6-7: reinforcement of floor slabs…
Facade works, laying of external sewerage pipes, installation of plasterboard framework of internal partitions, installation of metal fences, diamond drilling…
Villas — The site is undergoing foundation planning in the area of villas 10-14, movement of construction materials, installation of column formwork on villas 3…
Ceramic block masonry continues in Blocks A and B.
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st