Villas — The installation of formwork and reinforcement of the foundations of the villas, as well as the installation of formwork for the capital fence of the…
Construction progress, complex updates and real estate investment news from Batumi
Villas — The installation of formwork and reinforcement of the foundations of the villas, as well as the installation of formwork for the capital fence of the…
On the 3rd floor of block A the walls are being laid with ceramic block. Reinforcement of columns continues in Block B.
In Block B - reinforcement of vertical structures In Block C - concreting of the floor slab. In Block E, staircase formwork is being assembled and ceramic block…
On the 1st construction (Ground Floor) floor, the laying of walls with ceramic block continues. On the 13th (12th) floor the mocap is being built. Balcony…
Installation of heating, cold/hot water supply systems, laying of elevator portals from gas-silicate block, installation of GPB in common areas and installation…
The following types of works are in progress: - reinforcement and installation of formwork for villa foundations - installation of site fence formwork
Family Club — Block A - masonry of ceramic block walls on 3 floors Block B - reinforcement of vertical structures
Waterproofing of the retaining wall continues in Block B. Staircase reinforcement is underway in Block E.
Aqua — Loading of ceramic block on the floors is in progress. On the 1st construction (Ground Floor) floor the walls are being laid with ceramic block. On the…
Installation of cold/hot water supply systems, heating and laying of elevator portals with gas-silicate block.
Reinforcement of the foundations of the villas and the capital fence is underway.
Reinforcement of vertical structures continues in Building B.
In Block E, the installation of stairway formwork continues.
The mocap continues on the 13 construction (12 hotel) floor.
Installation of cold and hot water supply and heating systems is in progress. The screed and gas-silicate block of elevator portals are also being installed.
Villas — Reinforcing of foundations is in progress, concreting of the base of the complex fence has been carried out.
In block A the laying of ceramic block walls on the 3rd floor continues.
Riviera — In Block B, the waterproofing of the retaining wall is being applied. The drainage system is also being installed.
The mocap on the 13th floor and the framing of the balconies on the floors are in progress.
Outside, roofing works and waterproofing of balconies are in progress. Installation of cold/hot water supply systems, heating systems, screeding and framing…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st