In Block A, ceramic blockwork is being laid on the second floor. In Block B the floor slab formwork is being dismantled. Fireplaces are being installed in block…
Construction progress, complex updates and real estate investment news from Batumi
In Block A, ceramic blockwork is being laid on the second floor. In Block B the floor slab formwork is being dismantled. Fireplaces are being installed in block…
Aqua — Installation of monolithic balcony framing boards continues on the 7th construction (6 hotel) floor. Installation of profiles for the installation of…
Waterproofing of sanitary facilities is being carried out. Roofing works and terrace construction, installation of cold and hot water supply systems are in…
Lifting of ceramic block. Lifting of profiles for construction of GPB partitions.
Riviera — In Block B the reinforcement of the staircase is being carried out. In Block C, the installation of the vertical structure formwork continues.
Concreting of the floor slab has taken place in Block B.
Aqua — Installation of monolithic sides of balcony framing continues on the 7th construction (6 hotel) floor. Lifting of ceramic block.
Waterproofing of sanitary facilities is being carried out. Roofing and facade works, installation of cold and hot water supply systems, arrangement of terraces…
On the 3rd floor of Block A, the walls are being laid with ceramic block. In Block C, the installation of vertical structure formwork continues.
Waterproofing of bathrooms has been started. Roofing and facade works, installation of HTW and HTW systems, storm water drainage, terrace construction are in…
Earthwork is underway on the property.
Family Club — Ceramic block masonry walls are being laid on the 2nd floor of Block A. On the 3rd floor of Block B, the installation of the floor slab formwork…
Aqua — Construction of monolithic sides of balcony framing continues on the 7th construction (6th hotel) floor. Pilot installation of windows has started.
Facade and roofing works, installation of storm water drainage and HTW and HTW systems, terrace construction are in progress.
The excavation is underway.
Block A - laying of walls with ceramic block on the 2nd floor. Block B - reinforcement of the floor slab.
Block A - laying of walls with ceramic block on the 3rd floor. Block B - dismantling of floor slab formwork. Block C - installation of vertical structures…
Aqua — Building materials are being loaded onto the floors. On the 7th construction (6th hotel) floor the monolithic framing of the balconies is under…
Facade works, installation of warm floors, cold and hot water supply systems, storm water system, terrace construction are in progress.
Excavation work continues.
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st