Family Club — In Block A, reinforcement of the roof outlet cover slab is being carried out, and laying of walls with ceramic block on the 2nd floor continues.
Construction progress, complex updates and real estate investment news from Batumi
Family Club — In Block A, reinforcement of the roof outlet cover slab is being carried out, and laying of walls with ceramic block on the 2nd floor continues.
In block A on the 2nd floor the walls are being laid with ceramic block. In block B the floor slab formwork is being assembled. Reinforcement of vertical…
Aqua — On the 4th construction floor (3 hotel floors) the installation of technological openings is in progress. On the 7th (6th) floor the installation of…
Plastering works have been completed, facade works and masonry of internal partitions on the 1st floor are in progress. Hot and cold water supply systems…
Excavation and fencing of the site is underway.
Family Club — Block A - reinforcing of the roof exit slab is being done, laying of walls with ceramic block on the 2nd floor continues.
In block A on the 2nd floor the walls are being laid with ceramic block. In Block B, the floor slab formwork is being assembled. In block C - reinforcement of…
Aqua — On the 4th construction floor (3 hotel floors) the installation of technological openings is in progress. On the 7th (6th) floor the installation of…
Outside, the facade works are in progress. Inside, the walls are being plastered, cold and hot water supply communications are being installed, and internal…
Excavation and installation of site fencing is underway.
On the 2nd floor of block A, the laying of walls with ceramic block continues.
On the 2nd floor of block A the walls are being laid with ceramic block. On the 1st floor of Block B, the floor slab formwork is being assembled. In Block C…
Aqua — Installation of technological openings has started on the 4th construction (3 hotel) floor. Installation of balcony framing boards continues on the 7th…
Villas — Commencement of Work. Excavation of the excavation, installation of fencing and temporary road construction are in progress.
Block A - concreting of vertical structures, laying of walls with ceramic block.
Block A - on the 2nd floor the walls are being laid with ceramic block. Block C - installation of retaining wall formwork is in progress. Infrastructure…
Aqua — On the 7th construction (6 hotel) floor the installation of balcony framing boards is in progress. On the 6th (5) floor, technological openings are being…
Plastering and facade works are in progress.
Family Club — On the 2nd floor of Block A, wall masonry with ceramic block continues. Preparation for concreting of vertical structures was carried out on the…
Wall masonry with ceramic block is underway in Block A. Concreting of the floor slab and columns has been carried out in Block B. Installation of retaining wall…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st