Family Club — On the 2nd floor of block A the walls are being laid with ceramic block. On the 3rd floor of block B - reinforcement of the floor slab.
Construction progress, complex updates and real estate investment news from Batumi
Family Club — On the 2nd floor of block A the walls are being laid with ceramic block. On the 3rd floor of block B - reinforcement of the floor slab.
On the 3rd floor of block A the walls are being laid with ceramic block. In Block B, the floor slab formwork is being dismantled. In block C - installation of…
Aqua — On the 7th construction (6 hotel) the monolithic sides of the framing of balconies continue to be installed.
Facade works continue. Roofing, basement waterproofing and vapor barrier of terraces are being installed. Cold and hot water supply systems are being installed.
Land work is underway.
Family Club — In block A, concreting of the floor slab of the roof exit has taken place, the laying of walls with ceramic block on the 2nd floor is in progress.
In block A on the 3rd floor the walls are being laid with ceramic block. In Block B, the floor slab formwork is being assembled. In Block C, the formwork of…
Aqua — On the 4th construction floor (3 hotel floors) the installation of technological openings is in progress. On the 7th (6th) floor the installation of…
Facade works and masonry of internal partitions on the 1st floor are in progress. Roofing and waterproofing of the basement is in progress. Installation of…
Land work is underway.
Family Club — In Block A, reinforcement of the roof outlet cover slab is being carried out, and laying of walls with ceramic block on the 2nd floor continues.
In block A on the 2nd floor the walls are being laid with ceramic block. In Block B, the floor slab formwork is being assembled. In block C, concreting of the…
Aqua — On the 3rd construction (2 hotel) floor, the installation of technological openings is in progress. On the 8th (7th) floor the installation of balcony…
Facade works and masonry of internal partitions on the 1st floor are in progress. Roofing and waterproofing of the basement are in progress.
Land work is underway.
Family Club — In Block A, reinforcement of the roof outlet cover slab is being carried out, and laying of walls with ceramic block on the 2nd floor continues.
In block A on the 2nd floor the walls are being laid with ceramic block. In block B the floor slab formwork is being assembled. Reinforcement of vertical…
Aqua — On the 4th construction floor (3 hotel floors) the installation of technological openings is in progress. On the 7th (6th) floor the installation of…
Plastering works have been completed, facade works and masonry of internal partitions on the 1st floor are in progress. Hot and cold water supply systems…
Land work is underway.
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st