1. Installation of engineering systems.
— Electrical installation, 17th floor.
— Installation of ventilation system, 7.
2. Installation of elevator shafts.
Installation of elevator equipment.
3. Arrangement of gypsum cardboard frame.
Arrangement of the framework of partitions.
4. finishing works, 20th floor.
Laying tiles on the balconies.
5. Plastering works.
Plastering of balconies.
6. Arrangement of curbs for installation of stained glass windows.
Pouring curbs.
7. Waterproofing works.
Waterproofing of balconies in the units.
8. Masonry works, 10th floor.
Ceramoblock masonry.
9. Infrastructure building.
— Reinforcement of walls of the 2nd floor.
— Concreting of columns of the 2nd floor.