Wyndham Grand Batumi Gonio. Aqua.

1. Installation of engineering systems.

— Electrical work, wiring.

— Plumbing work, 17th floor.

— Installation of air conditioning pipes, 12th floor.

— Installation of ventilation system.

2. Installation of plasterboard frame, 8th-9th floors.

Installation of frame for inter-unit partitions, insulation of inter-unit partitions.

3. Finishing works, 9th floor.

Laying tiles on balconies.

4. Installation of a panoramic lift.

Concreting of panoramic lift slabs.

5. Infrastructure building.

— Concreting of vertical structures, 7th floor.

— Laying of ceramic blocks, 3rd floor.