Block A 1. Plastering work. Plastering of slopes. 2. Facade work. — Facade and slope cladding with clinker tiles. — Plastering of the facade. 3. Installation of…
Construction progress, complex updates and real estate investment news from Batumi
Block A 1. Plastering work. Plastering of slopes. 2. Facade work. — Facade and slope cladding with clinker tiles. — Plastering of the facade. 3. Installation of…
1. Installation of engineering systems. Electrical installation work, installation of electrical cables and clips, 6th floor. 2. Installation of elevator…
1. Monolithic works. Installation of formwork for floor slabs on the 2nd floor of villas 15 and 16.
1. Block A. Installation of engineering systems. Hot and cold water supply layout. 2. Block B. Installation of engineering systems. — Hot and cold water supply…
Block A 1. Plastering work. Plastering of slopes. 2. Facade work. — Facade and slope cladding with clinker tiles. — Plastering of the facade. Block B. 1…
1. Installation of engineering systems. Electrical installation work, electrical cable installation, 6th floor. 2. Installation of elevator shafts. Installation…
Block A 1. Plastering work. Plastering of slopes. Block B. 1. Installation of stained glass structures. Installation of stained glass and glass. Other…
1. Installation of engineering systems. Electrical installation work, installation of clips. 2. Installation of elevator shafts. Installation of elevator…
1. Monolithic works. Installation of formwork for floor slabs on the 2nd floor of villas 15 and 16. 2. Installation of a fence around the complex. Installation…
1. Blocks A and B. Installation of engineering systems. Hot and cold water supply layout. 2. Block A. Waterproofing of chimney flues. 3. Blocks B and C…
Block A 1. Plastering work. — Plastering of slopes, 3rd floor. — Plastering of the facade, installation of beacons for plastering. 2. Finishing work…
1. Installation of engineering systems. Electrical installation work. 2. Installation of elevator shafts. Installation of elevator equipment. 3. Installation of…
1. Monolithic works. Installation of formwork for the floor slab on the 2nd floor of villa 15. 2. Installation of a fence around the complex. Installation of…
1. Blocks A and B. Installation of engineering systems. Hot and cold water supply layout. 2. Block A. Waterproofing of chimney flues. 3. Blocks B and C…
Block A 1. Plastering work. — Plastering of slopes, 3rd floor. — Plastering of the facade, installation of beacons for plastering. 2. Finishing work…
1. Installation of engineering systems. Plumbing work, installation of fixtures. 2. Installation of elevator shafts. Installation of elevator equipment. 3…
1. Monolithic works. Installation of formwork for the floor slab on the 2nd floor of villa 15. 2. Installation of side walls for the installation of stained…
1. Blocks B and C. Construction of rear courtyards for townhouses. 2. Block B. Facade work. Plastering of facade ends. 3. Block E. Installation of engineering…
Block A 1. Plastering work. Plastering of slopes. 2. Finishing work. Installation of ceramic granite floor tiles on the balcony. 3. Facade work. — Facade…
1. Installation of engineering systems. Plumbing work, installation of fixtures. 2. Installation of elevator shafts. Installation of elevator equipment. 3…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st