Facade, roofing and plastering works are performed.
Construction progress, complex updates and real estate investment news from Batumi
Facade, roofing and plastering works are performed.
Reinforcing of the floor slab is underway on the roof of Block A, and ceramic block walls are being laid on the 1st floor. Block B - reinforcement of columns is…
Ceramic block walls are being laid on the 1st and 2nd floors of Block A. Reinforcement of the floor slab continues in Block B. Earthworks are underway in block…
On the floors the monolithic sides of the balcony framing are under construction.
Facade works on the exterior and plastering works on the interior are in progress. Electricity and gas supply networks are being wired on the floors.
Block A - laying of walls with ceramic block on the 1st floor and installation of formwork for the floor slab above the 5th floor. Block B - reinforcement of…
On the floors, the construction of technological openings and monolithic sides of the balcony framing is in progress. Capital fencing of the complex is being…
Wall masonry with ceramic block continues in Block A. Reinforcement of the floor slab is underway in Block B. Earthworks are underway in Block C. Dismantling of…
Facade and plastering works are in progress. Gas and electric utilities are being installed on the floors.
In block A the walls are being laid with ceramic block on the 1st floor. Reinforcement of the floor slab on the 5th floor is in progress. Concreting of the…
In Block A, wall masonry with ceramic block continues. Concreting of the floor slab has been carried out in Block B. Excavation works are underway in Block C…
Aqua — On the 3rd construction (2 hotel) floor, formwork installation, reinforcement and concreting of monolithic balcony framing boards are in progress…
Facade and plastering works are in progress. Installation of electrical and gas utilities is in progress.
On the 1st floor of Block A, wall masonry with ceramic block continues, the floor slab is being reinforced above the 5th floor. Reinforcement of the floor slab…
Block A - ceramic block wall masonry continues on the floors. Block B - reinforcement of the floor slab is in progress. Infrastructure building - reinforcement…
Aqua — Works on installation of the capital fence of the hotel continue on the territory. Technological openings are being made on the floors. Formwork…
Facade, plastering, electrical works and connection of gas utilities are in progress.
In Block A, reinforcement of the floor slab above the 5th floor and laying of walls with ceramic block on the 1st floor continues. Reinforcement of the floor…
Кладка стен керамическим блоком идет на 2 этаже блока А. В блоке B продолжается армирование плиты перекрытия. Армирование колонн производится в инфраструктурном…
Aqua — Technological openings continue to be installed on the floors. Works on installation of capital fencing are underway on the territory.
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st