Concreting of the tank has been carried out. Facade and plastering works are in progress. Electrical lighting systems and power equipment are being wired on the…
Construction progress, complex updates and real estate investment news from Batumi
Concreting of the tank has been carried out. Facade and plastering works are in progress. Electrical lighting systems and power equipment are being wired on the…
Concreting of the 2nd stage of the staircases was carried out on the 5th floor of Block A. On the 1st floor, the walls are being laid with ceramic block. In…
Block A - on the 2nd floor ceramic block walling is in progress. Infrastructure building - reinforcement of the floor slab is in progress.
Aqua — Work is underway to install process openings on the floors and capital fencing on the property.
Plastering works, wiring of electrical lighting systems and power equipment are in progress, and a reservoir is being built on the territory.
On the 1st floor of Block A, the wall masonry with ceramic block continues. In Block B, the formwork for the floor slab of the 3rd floor is being assembled.
In Block A, the walls are being laid with ceramic block.
Aqua — Capital fencing continues to be installed on the territory. On the 19th construction (18th hotel) floor the walls are being masoned with ceramic block…
Plastering works on the floors are in progress. A reservoir is being built on the territory.
On the 1st floor of Block A, wall masonry with ceramic block continues, and the floor slab formwork is being installed above the 5th floor. In Block B, the…
Riviera — On the 2nd floor of Block A, wall masonry with ceramic block is in progress. Concreting of the foundation slab and retaining wall was carried out in…
Aqua — Marking of technological openings continues on the floors. Capital fencing of the hotel is being installed on the territory.
Plastering works and installation of gasification systems continue on the floors.
On the 1st floor of Block A, wall masonry with ceramic block continues, the floor slab formwork is being assembled above the 5th floor. Installation of floor…
Loading of ceramic block on the floors and laying of walls on the 2nd floor is carried out in Block A. In Block B the ballast is being backfilled. Foundation…
Aqua — On the 19th construction floor (18 hotel floors) the ceramic block is being lifted and the walls are being laid. Technological openings are being made on…
Plastering works are in progress. Installation of gasification systems for the units has started.
Family Club — Block A - masonry walls with ceramic block on the 1st floor and installation of the floor slab formwork above the 5th floor. Block B…
On the 2nd floor of Block A, wall masonry with ceramic block continues. Dismantling of the floor slab formwork is underway in Block B. Reinforcement of the…
Aqua — Ceramic block wall masonry continues on the 19th construction floor (18 hotel floors). Measurements are being taken on the floors for the installation of…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st