Installations are being installed in the bathrooms. Plastering works on the floors and facade works on the exterior.
Construction progress, complex updates and real estate investment news from Batumi
Installations are being installed in the bathrooms. Plastering works on the floors and facade works on the exterior.
Reinforcement and installation of column formwork on the roof is underway in Block A. Laying of walls with ceramic block on the 2nd floor has been started. In…
Riviera — Block A - masonry of walls with ceramic block is going on the 2nd floor. Block B - reinforcement of columns. Block C - preparation for column…
Aqua — On the 9th construction (8 hotel) floor the installation of technological openings is in progress. On the 4th (3) floor, formwork installation…
Facade and plastering works are in progress, as well as the installation of vertical routes for electrical equipment and lighting, and installation of…
On the 1st floor of block A the walls are being laid with ceramic block. In Block B, the floor slab formwork is being assembled.
On the 1st floor of Block A, wall masonry with ceramic block continues. The floor slab formwork is being assembled in Block B. Floor slab formwork is being…
Aqua — On the 10th construction (9 hotel) floor, technological openings are being made. On the 4th (3) floor the installation of balcony framing boards is in…
Plastering and facade works are in progress. Installation of installations in bathrooms, vertical routes of electrical equipment and lighting, and gas…
On the 1st floor of block A the walls are being laid with ceramic block. On the 3rd floor of Block B, the floor slab formwork is being assembled.
Block A - the walls are being laid with ceramic block. Block B - reinforcement of vertical structures is in progress. Block C - excavation works are in…
Aqua — On the 10th construction floor (9 hotel floors), technological openings are being made. On the 4th (3) reinforcement, formwork installation and…
Facade and plastering works are in progress. Gas and electric utilities are being installed. Installations are being installed in the bathrooms.
Family Club — In block A on the 1st floor, the walls are being laid with ceramic block. In Block B, the floor slab formwork is being assembled.
Ceramic block walls are being laid on the 1st and 2nd floors of Block A. In Block B, reinforcement of vertical structures is being carried out. Ground works are…
Installation of monolithic balcony framing boards continues on the 4th (3rd) floor.
Facade and plastering works are in progress. Gas and electric utilities are being installed. Installations are being installed in the bathrooms.
Family Club — In block A on the 1st floor, the walls are being laid with ceramic block. In Block B, the floor slab formwork is being assembled.
Ceramic block walls are being laid on the 1st and 2nd floors of Block A. In Block B, reinforcement of vertical structures is being carried out. Ground works are…
Installation of monolithic balcony framing boards continues on the 4th (3rd) floor.
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st