Block A - block masonry on the floors is in progress. Block B - dismantling of formwork and reinforcement of vertical structures of the 2nd stage. Block C…
Construction progress, complex updates and real estate investment news from Batumi
Block A - block masonry on the floors is in progress. Block B - dismantling of formwork and reinforcement of vertical structures of the 2nd stage. Block C…
Aqua — Ceramic block wall masonry continues on the 18th construction (17 hotel) floor. Loading of building materials is going on the 19th (18th) floor.
Block A - masonry of walls with ceramic block. Block B - dismantling of formwork of vertical structures of the 1st stage, reinforcement of vertical structures…
Aqua — Ceramic block wall masonry continues on the 17th building (16 hotel) and has begun on the 18th (17) floors.
Electrical installation and facade works are in progress. Preparatory work for plastering is underway.
Formwork installation and reinforcement of the floor slab of the 5th floor continues in Block A, reinforcement of staircases has started. Reinforcement of…
Family Club — Formwork installation and reinforcement of the floor slab of the 5th floor of Block A continues. Concreting of the floor slab of the basement…
Riviera — Laying of walls and internal partitions continues in Block A. Reinforcement of the 2nd stage of vertical structures has started in Block B. Earthworks…
On the 17th construction (16 hotel) floor the walls are being masoned with ceramic block.
Facade works and preparatory works for plastering are in progress. Installation of electrical systems on the floors is in progress.
Facade works, preparatory works for plastering and installation of electrical systems are underway.
Family Club — Formwork installation and reinforcement of the floor slab of the 5th floor continues in Block A. Reinforcement of the basement floor slab…
Riviera — Ceramic block walls are being laid in Block A. Concreting of the walls of the basement floor of Phase 1 has been carried out in Block B. Reinforcement…
On the 17th construction (16 hotel) floor the walls are being masoned with ceramic block.
Electrical work is underway on the floors.
Block A - formwork installation and reinforcement of the floor slab of the 5th floor. Block B - reinforcement of the basement floor slab.
Riviera — Block A - masonry of walls with ceramic block. Block B - installation of formwork of the 1st stage of vertical structures and reinforcement of the 2nd…
On the 17th construction (16 hotel) floor the walls are being masoned with ceramic block.
Facade and electrical works continue, and walls are being prepared for plastering.
Formwork installation and reinforcement of the floor slab of the 5th floor is in progress in Block A. Reinforcement of the basement floor slab is underway in…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st