Block A - completion of reinforcement of the 5th floor floor slab. Block B - concreting of the 1st stage of columns.
Construction progress, complex updates and real estate investment news from Batumi
Block A - completion of reinforcement of the 5th floor floor slab. Block B - concreting of the 1st stage of columns.
Riviera — Block A - masonry walls with ceramic block and geodetic surveying. Block B - concreting of floor slab Block D - earthworks Infrastructure building…
On the 19th construction (18 hotel) floor the walls are being laid with ceramic block.
Facade works, electrical works, installation of plaster beacons and plastering of walls are in progress.
Family Club — Formwork installation and reinforcement of the floor slab is going on in Block A. Formwork installation and reinforcement of the 1st stage of…
In the infrastructure building, the installation of the vertical structure formwork is in progress. In Block A, the masonry walls are being laid with ceramic…
Aqua — On the 19th construction (18 hotel) floor, the laying of walls with ceramic block continues.
Installation of electrical systems, stained glass windows and plaster beacons is in progress. Plastering of walls has started.
Block A - formwork installation and reinforcement of the 5th floor floor slab. Block B - reinforcement of the 1st stage of columns.
Riviera — Ceramic block wall masonry continues in Block A. In Block B, the floor slab formwork is being assembled. Excavation works are being carried out in…
On the 19th construction (18 hotel) floor the walls are being laid with ceramic block.
Facade works, electrical installation works on the floors are in progress. Installation of plaster beacons has started.
Family Club — Installation of the 5th floor slab formwork continues in Block A. Reinforcement of the 1st stage of columns - in Block B.
In Block A, the walls are being laid with ceramic block. In Block B - installation of the floor slab formwork. In block D - excavation works. Infrastructure…
Ceramic block wall masonry continues on the 19th construction (18 hotel) floor.
Facade works are underway on the exterior, while the installation of electrical systems continues inside the building. On the roof, shafts are being laid.
Block A - formwork installation and reinforcement of the 5th floor floor slab. Block B - reinforcement of the 1st stage of columns.
Riviera — Ceramic block wall masonry continues in Block A. In Block B, dismantling of the vertical structure formwork and installation of the floor slab…
On the 19th construction (18 hotel) floor the walls are being laid with ceramic block.
Facade works are carried out on the outside and electrical works are carried out on the inside.
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st