Internal electrical and lighting systems are being installed on the floors.
Construction progress, complex updates and real estate investment news from Batumi
Internal electrical and lighting systems are being installed on the floors.
Riviera — Ceramic block wall masonry continues in Block A. Pouring of the 2nd stage of the concrete foundation preparation has been carried out in Block B…
Aqua — Ceramic block wall masonry continues on the 16th construction (15 hotel) and 18th (17) floors.
Reinforcement of the walls of the swimming pool area continues in the territory. Internal electrical and lighting systems are being installed on the floors, as…
Family Club — In Block A, the installation of the floor slab formwork for the 5th floor continues. Installation of the slab formwork at 0.00 is underway in…
Excavation works for the foundation of the infrastructure building are in progress. Ceramic block walling is underway in Block A. Reinforcement of the basement…
Aqua — Ceramic block wall masonry continues on the 16th construction (15th hotel) and 18th (17th) floors.
Internal electrical and lighting systems are being installed in the units.
Block A - installation of the floor slab formwork on the 5th floor. Block B - installation of floor slab formwork at 0.00.
Excavation works for the foundation excavation of the infrastructure building continue. In Block A, the walls are being laid with ceramic block and geodetic…
Aqua — On the 16th construction (15 hotel) and on the 18th (17) floors, the walls are being masoned with ceramic block.
Installation of internal electrical and lighting systems continues on the floors.
Work is underway on the installation of internal electrical and lighting systems.
Family Club — Block A - installation of the floor slab formwork on the 5th floor. Block B - installation of floor slab formwork at 0.00.
Riviera — In Block A the walls are being laid with ceramic block. Excavation works are being carried out in Block C. An excavation is underway at the site of…
Aqua — Ceramic block wall masonry is underway on the 16th building (15 hotel) as well as on the 18th (17th) floors.
Internal electrical and lighting systems are being installed on the floors.
Family Club — Installation of the floor slab formwork on the 5th floor continues in Block A. Installation of the floor slab formwork at 0.00 is underway in…
Riviera — Excavation works on the site of the infrastructure building continue. In Block A, geodetic surveying and ceramic block walling is in progress.
Aqua — On the 16th construction (15th hotel) and 18th (17th) floors the walls are being laid with ceramic block. Loading of construction materials on the floors…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st