Formwork installation and reinforcement of the floor slab of the 5th floor continues in Block A. In Block B, reinforcement of vertical structures of the…
Construction progress, complex updates and real estate investment news from Batumi
Formwork installation and reinforcement of the floor slab of the 5th floor continues in Block A. In Block B, reinforcement of vertical structures of the…
In Block A, the walls are being laid with ceramic block. In Block B, the vertical structure formwork is being dismantled and the floor slab formwork is being…
On the 19th construction (18 hotel) floor the walls are being masoned with ceramic block.
Facade works are being carried out on the outside, electrical installation and preparatory works for plastering on the inside. Work on the swimming pool is in…
Formwork installation and reinforcement of the floor slab of the 5th floor continues in Block A. In Block B, reinforcement of vertical structures of the…
In Block A, the walls are being laid with ceramic block. In the infrastructure building, the formwork of vertical structures is being assembled.
On the 19th construction (18 hotel) floor the walls are being masoned with ceramic block.
Facade works are being carried out on the outside, electrical installation and preparatory works for plastering on the inside. Work on the swimming pool is in…
Formwork installation and reinforcement of the floor slab of the 5th floor continues in Block A. Reinforcement of vertical structures of the basement floor is…
In Block A the walls are being laid with ceramic block. Concreting of the second stage of vertical structures took place in Block B. As well as concreting of…
On the 19th construction (18 hotel) floor the walls are being masoned with ceramic block.
Facade works are being carried out on the outside, electrical installation and preparatory works for plastering on the inside. Work on the swimming pool is in…
Formwork installation and reinforcement of the floor slab of the 5th floor continues in Block A. Reinforcement of the basement floor slab continues in Block B.
In Block A the walls are being masoned with ceramic block. In Block B, reinforcement of the second stage of vertical structures continues. Reinforcement of the…
On the 19th construction (18 hotel) floor the walls are being masoned with ceramic block.
Family Club — Formwork installation and reinforcement of the floor slab of the 5th floor continues in Block A. Reinforcement of the basement floor slab…
Riviera — Wall masonry with ceramic block is going on in Block A. Reinforcement of the 2nd stage of vertical structures is going on in Block B. Earthworks - in…
On the 18th construction (17 hotel) floor the walls are being masoned with ceramic block.
Facade works are being carried out outside, inside - electrical installation and preparatory works for plastering.
Family Club — In Block A, formwork installation and reinforcement of the floor slab of the 5th floor, as well as reinforcement of the staircases continues. In…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st