Concreting of the base of the swimming pool has been carried out. Installation of internal electrical and lighting systems continues in the units.
Construction progress, complex updates and real estate investment news from Batumi
Concreting of the base of the swimming pool has been carried out. Installation of internal electrical and lighting systems continues in the units.
Block A - installation of the floor slab formwork on the 5th floor. Block B - installation of floor slab formwork at 0.00.
In Block A, marking is being carried out and masonry walls are being laid with ceramic block. The excavation for the construction of the infrastructure building…
Aqua — Ceramic block wall masonry continues on the 16th construction (15th hotel) and 18th (17th) floors. Loading of construction materials on the floors is in…
Work continues on the swimming pool and installation of electrical systems.
Family Club — Installation of the floor slab formwork on the 5th floor is underway in Block A. In Block B, the installation of the floor slab formwork continues…
Riviera — In Block A, masonry walls are being laid with ceramic block on the floors. Excavation for the infrastructure building has started.
Aqua — Ceramic block wall masonry continues on the 16th construction (15th hotel) floor. Marking has been carried out and masonry work has started on the 18th…
Work is underway on fireplaces, bases for balcony enclosures, swimming pool, and installation of internal electrical systems.
Family Club — In Block A, the floor slab formwork of the 5th floor is being assembled. In Block B - installation of floor slab formwork at 0.00.
In Block A, block masonry on the floors is in progress. In Block B, reinforcement of the 2nd stage of the foundation slab is in progress. Excavation works are…
Aqua — Monolithic frame works on the site have been completed with concreting of lift shaft covers. On the 16th construction floor (15th hotel floor) the…
Foundations for balcony railings are being built and fireplaces are being laid on the 6th construction (5th residential) floor. Work on the swimming pool is in…
Family Club — Installation of the formwork for the floor slab of the 5th floor of Block A continues. The formwork for the third stage of the basement walls and…
In Block A, the walls are being laid with ceramic block. Reinforcement of the second stage of the foundation slab is in progress in Block B. Land works are…
On the 16th construction (15th hotel) floor the walls are being laid with ceramic block.
The installation of internal electrical systems on the floors, the construction of bases for balcony enclosures and the laying of fireplaces on the 6th…
Family Club — Installation of the formwork for the floor slab of the 5th floor of Block A continues. In Block B, concreting of the basement vertical structures…
In Block A, the walls are being laid with ceramic block. Reinforcement of the second stage of the foundation slab is in progress in Block B. Land works are…
On the 16th construction (15th hotel) floor the walls are being laid with ceramic block.
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st