The installation of internal electrical systems on the floors, the construction of bases for balcony enclosures and the laying of fireplaces on the 6th…
Construction progress, complex updates and real estate investment news from Batumi
The installation of internal electrical systems on the floors, the construction of bases for balcony enclosures and the laying of fireplaces on the 6th…
Family Club — Installation of the formwork for the floor slab of the 5th floor of Block A continues. In Block B, the formwork for the 3rd stage of the basement…
Riviera — In Block A, the walls are being laid with ceramic block. Reinforcement of the 2nd stage of the foundation slab continues in Block B. Earthworks are…
Aqua — Ceramic block wall masonry continues on the 16th construction (15th hotel) floor. Preparation for concreting of lift shaft covers is carried out on the…
The construction of the swimming pool is in progress. On the 6th (5th) floor the fireplaces are being laid. On the floors, the bases for balcony railings and…
Block A - installation of the 5th floor slab formwork. Block B - installation of formwork for the 3rd stage of the basement wall and formwork for the floor slab…
Riviera — Block A - laying of walls with ceramic block Block B - reinforcement of foundation slab Block C - earthworks Block E - laying of walls and partition…
Aqua — Ceramic block wall masonry is going on the 16th construction (15th hotel) floor. Installation of the formwork for the floor slabs of the lift shaft exits…
Family Club — In Block A, the installation of the 5th floor slab formwork continues. In Block B, the formwork for the 3rd stage of the basement wall and the…
In Block A, the laying of walls with ceramic block has started. Loading of the block on the floors is in progress. Reinforcement of the 2nd stage of the…
Aqua — On the roof, the installation of formwork for the floor slabs of the lift shaft exits continues. On the 16th construction (15th hotel) floor the walls…
On the 6th (5th) floor the masonry of fireplaces is in progress. Installation of bases for balcony railings continues on the floors. The pool is being…
Work on the swimming pool is in progress. On the 6th (5th) floor the masonry of fireplaces is in progress. The bases for balcony railings are being installed on…
Block A - installation of the floor slab formwork has started. Block B - installation of formwork for the 3rd stage of the basement wall is in progress…
Riviera — In Block A, dismantling of the floor slab formwork is in progress. In Block B, installation of the foundation slab formwork. In block C - excavation…
Aqua — Reinforcement of structures continues on the roof. On the 16th construction floor (15th hotel floor) - laying of walls with ceramic block.
Work on the swimming pool is in progress on the territory. Fireplaces are being laid on the 6th building (5th residential). Installation of bases for balcony…
Family Club — Preparation for the installation of the 5th floor slab formwork is underway in Block A. In Block B, the formwork for the 3rd stage of the basement…
Riviera — In Block A, the dismantled formwork from the floors continues to be lowered. In Block B - reinforcement of the 2nd stage of the foundation slab…
Aqua — On the roof, the formwork for the floor slabs of the lift shafts is being installed. On the 16th construction floor (15th hotel floor), ceramic block…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st