The installation of the stained glass windows continues on the 3rd construction (2nd residential) floor.
Construction progress, complex updates and real estate investment news from Batumi
The installation of the stained glass windows continues on the 3rd construction (2nd residential) floor.
Family Club — Reinforcement of the floor slab continues on the 4th floor of Block A. Column reinforcement is underway in Block B.
Riviera — Dismantling of the floor slab formwork continues in Block A. In Block B, excavation works are in progress. In Block E, walls and partition walls are…
Aqua — Installation of the roof slab formwork continues above the 20th construction (19th hotel) floor. On the 14th (13th) and 15th (14th) floors the walls are…
Riviera — In Block E, the laying of walls and partitions with ceramic block continues, and arch lintels are being installed.
On the 14th (13th) and 15th (14th) floors the walls are being masoned with ceramic block.
In Block A, the installation of the floor slab formwork for the 4th floor continues.
Stained glass windows are being installed on the 2nd construction (1 residential) floor.
In Block E, walls and partition walls are being laid with ceramic block and arch lintels are being installed. Block B: excavation works are in progress.
On the 14th (13th) and 15th (14th) floors the walls are being masoned with ceramic block.
The masonry of internal partition walls on the floors is in progress. Stained glass windows are being installed on the 2nd construction (1 residential) floor.
In Block A, the installation of formwork for the floor slab of the 4th floor continues. Reinforcement of the basement floor columns is underway in Block B.
Riviera — Block A: dismantling of the floor slab formwork Block B: excavation works and concreting of the first part of the foundation preparation Block E…
Aqua — The roof slab formwork is being installed on the 20th construction (19th hotel) floor. On the 14th (13th) and 15th (14th) floors the walls are being laid…
Laying of walls with ceramic block on the floors continues. Installation of stained glass windows has started on the 2nd building (1 residential).
Block A: installation of the floor slab formwork for the 4th floor continues. Block B: reinforcement of the basement floor columns is in progress.
Dismantling of the floor slab formwork continues in Block A. Installation of staircase formwork has started. Excavation works are underway in Block B. In Block…
Aqua — Installation of the roof slab formwork continues. Ceramic block masonry walls are being laid on the 14th construction (13 hotel) and 15th (14) floors.
On the floors, the laying of walls with ceramic block continues.
Family Club — Reinforcement of the floor slab of the 4th floor has started in Block A. Reinforcement of the basement floor columns has started in Block B.
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st