Riviera — Block A: dismantling of the floor slab formwork is in progress Block B: excavation works are in progress Block E: ceramic block walls and arched…
Construction progress, complex updates and real estate investment news from Batumi
Riviera — Block A: dismantling of the floor slab formwork is in progress Block B: excavation works are in progress Block E: ceramic block walls and arched…
Aqua — On the 20th construction (19th hotel) floor, the installation of the roof slab formwork has started. On the 14th construction (13 hotel) and 15th (14)…
The laying of ceramic block walls on the floors and the installation of arched window openings is in progress.
Family Club — Block A: installation of floor slab formwork for the 4th floor is in progress Block B: marking of the basement floor columns has been carried out.
Riviera — Block A: dismantling of the floor slab formwork has started Block B: excavation works are in progress Block E: ceramic block wall masonry and…
Aqua — Concreting of columns was carried out on the 20th construction (19th hotel) floor. On the 14th (13th) and 15th (14th) floors, wall masonry with ceramic…
Work is in progress on ceramic block walls and installation of arched lintels. The building is connected to the city sewerage system.
Formwork for the 4th floor slab is being erected in Block A.
Block E - ceramic block wall masonry continues on the floors.
Aqua — Preparation for concreting of columns is underway on the 20th construction (19th hotel) floor. On 18 (17) - dismantling of the floor slab formwork. On 14…
Ceramic block masonry of internal walls continues on the 6th construction (5th residential) floor. Installation of supports for stained glass windows on the 2nd…
In block A the formwork for the floor slab of the 4th floor is being assembled.
Ceramic block wall masonry continues in Block E.
Aqua — On the 20th construction (19th hotel) floor, preparation for concreting of columns has been carried out. On the 14th (13th) and 15th (14th) floors, wall…
Masonry work continues on the 6th construction (5 residential) and 7th (6) floors.
Riviera — In Block E, the walls are being laid with ceramic block and the staircase formwork is being installed.
Installation of the formwork for the columns of the 20th construction (19th hotel) floor has been completed. Ceramic block walls on the 14th (13th) and 15th…
The laying of walls and internal partitions with ceramic block continues on the floors.
In Block A, the installation of formwork for the floor slab of the 4th floor continues. Concreting of the foundation slab was carried out in Block B.
Riviera — Block B: excavation works Block E: ceramic block masonry works are in progress, staircase formwork installation has begun
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st