Formwork installation of vertical structures is carried out.
Construction progress, complex updates and real estate investment news from Batumi
Formwork installation of vertical structures is carried out.
Riviera — In Block A, installation of formwork for the first floor slab (first half of the block) and reinforcement of the first floor vertical structures…
Work continues on installing the formwork for the 18th floor.
Ceramic block wall masonry continues on floors 4 (3) and 5 (4).
Formwork installation of vertical structures is carried out.
Riviera — In Block A, installation of formwork for the first floor slab (first half of the block) and reinforcement of the first floor vertical structures…
Work continues on installing the formwork for the 18th floor.
Ceramic block wall masonry continues on floors 4 (3) and 5 (4).
Family Club — Reinforcement and formwork installation of staircases and vertical structures is in progress. Dismantling of the formwork of horizontal structures…
Riviera — In Block A, the installation of formwork for the first floor slab (first half of the block) and reinforcement of vertical structures of the first…
Work continues on installing the formwork for the 18th floor.
Ceramic block wall masonry continues on floors 4 (3) and 5 (4).
Wyndham Grand Residences Batumi Gonio.Family Club — Reinforcement and formwork installation of vertical structures is in progress. Dismantling of the vertical…
— In Block A, installation of formwork for the first floor slab (first half of the block) and reinforcement of the first floor vertical structures (second half…
The laying of walls with ceramic block on the 8th floor continues.
Ceramic block wall masonry continues on floors 4 (3) and 5 (4).
Reinforcement and installation of staircase formwork continues. Dismantling of formwork and reinforcement of vertical structures is in progress.
Riviera — In Block A, the installation of formwork for the first floor slab (first half of the block) continues and reinforcement of the first floor vertical…
The laying of walls with ceramic block on the 8th floor continues.
Ceramic block wall masonry continues on floors 4 (3) and 5 (4).
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st