Ceramic block wall masonry continues on the 4th construction (3 residential) and 5th (4) floors.
Construction progress, complex updates and real estate investment news from Batumi
Ceramic block wall masonry continues on the 4th construction (3 residential) and 5th (4) floors.
Dismantling of the 1st stage column formwork after concreting is in progress and installation of the 2nd stage column formwork has started.
In Block A, the floor slab formwork is being erected in the 1st half of the block and column reinforcement in the 2nd half. Excavation works are underway in…
Aqua — The formwork for the floor slab of the 18th (17th construction) floor is being assembled. Ceramic block walls are being laid on floors 8 (7) and 9 (8).
On the 4th construction (3 residential) and 5th construction (4 residential) floors, ceramic block walls are being masoned.
After the earlier concreting of the columns on the 2nd floor, the dismantling of the formwork began.
Block A: Installation of formwork for the floor slab of the 2nd floor in the 1st half is in progress. Reinforcement of the 2nd floor columns is in progress in…
Ceramic block masonry walls are being laid on the 8th construction (7 hotel) floor.
Ceramic block wall masonry continues on the 4th (3 residential) and 5th (4) floors. Loading of construction materials on the floors has been carried out.
Concreting of staircases and columns of the 2nd floor was carried out.
— In Block A, in the 1st half, installation of formwork for the 2nd floor slab continues. In the 2nd half reinforcement of the 2nd floor columns. Excavation…
Ceramic block wall masonry continues on Building 4 (3 residential) and Building 5 (4).
Dismantling of the floor slab formwork of the 2nd floor is in progress. Work has started on the installation of formwork for the floor slab of the 3rd floor.
Riviera — Block A In the 1st half, installation of formwork for the 2nd floor floor slab is in progress. In the 2nd half - reinforcement of columns of the 2nd…
Aqua — Work is underway to install the formwork for the floor slab of the 18th construction (17th hotel) floor.
Ceramic block masonry walls are being laid on the 4th construction (3 residential) and 5th (4) floors.
After the concrete has gained strength, the slab formwork is dismantled.
Riviera — On the 2nd floor in the 2nd part of the block A works on installation of the column formwork are in progress, in the 1st part of the block…
Aqua — Work continues on the installation of the formwork for the floor slab of the 18th construction (17th hotel) floor.
Ceramic block wall masonry continues on floors 4 (3) and 5 (4).
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st