Ceramic block wall masonry continues on Building 4 (3 residential) and Building 5 (4).
Construction progress, complex updates and real estate investment news from Batumi
Ceramic block wall masonry continues on Building 4 (3 residential) and Building 5 (4).
In Block A, work has started on the installation of formwork for the floor slab of the 3rd floor.
Riviera — In Block A on the 2nd floor, dismantling of the floor slab formwork in the 1st half has started, in the 2nd half dismantling of the column formwork…
Aqua — Reinforcement of the floor slab is underway on the 18th construction (17th hotel) floor. Work continues on wall masonry with ceramic block on floors 8…
Ceramic block masonry walls on the 4th construction (3 residential) and 5th (4) floors.
Concreting of the 3rd group of columns was carried out on the 2nd floor.
On the 2nd floor of Block A, the floor slab is concreted in the 1st part and the columns are concreted in the 2nd part. Excavation works continue in Block B.
Aqua — Work is underway to install the formwork for the floor slab of the 18th construction (17th hotel) floor. On 8 (7) and 9 (8) the ceramic block walls…
Ceramic block masonry walls are being laid on the 4th construction (3 residential) and 5th (4) floors.
The formwork of the 3rd group of columns of the 2nd floor is being assembled.
Riviera — In the second half of Block A on the 2nd floor, reinforcement of columns continues. Excavation works are underway in Block B.
Aqua — Ceramic block wall masonry continues on the 8th building (7 hotel) as well as the ninth (8th) floor.
Ceramic block walls are being laid on the 4th construction (3 residential) and 5th construction (4 residential) floors.
The formwork of the 3rd group of columns of the 2nd floor is being assembled.
In Block A, the floor slab formwork is being erected in the 1st half of the block and column reinforcement in the 2nd half. Excavation works are underway in…
Aqua — Installation of the floor slab formwork for the 18th construction (17th hotel) floor continues.
On the 4th construction (3 residential) and 5th construction (4 residential) floors, ceramic block walls are being masoned.
Installation of formwork of the third group of columns of the 2nd floor is in progress.
Riviera — Block A: Installation of the formwork for the 2nd floor slab in the 1st half is in progress. Reinforcement of the 2nd floor columns is underway in the…
Aqua — Formwork installation of the floor slab of the 18th construction (17th hotel) floor is in progress. Ceramic block wall masonry has started on the 9th (8)…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st