Facade works continue, laying of porcelain stoneware in mockup. Fire extinguishing system pipes, boiler pipes, gutters and sockets are being installed…
Construction progress, complex updates and real estate investment news from Batumi
Facade works continue, laying of porcelain stoneware in mockup. Fire extinguishing system pipes, boiler pipes, gutters and sockets are being installed…
Aqua — The site continues to pour concrete sides (framing) of balconies and their waterproofing, installation of gypsum cardboard framework of internal…
Family Club — Ceramoblock walls continue to be laid in blocks A and B. The floor slab formwork is also being installed in block B, on the fifth floor.
Villas — Waterproofing of villas and foundations continues. The foundations are also undergoing formwork removal and backfill compaction.
Riviera — Fireplaces are being installed in Block A. In Block B - laying of ceramic block walls and dismantling of the floor slab formwork. In Block C, the…
Facade works continue, porcelain stoneware is being laid in the mockup, painting works on the first floor are underway, and fire pipes, gutters and sub-sockets…
Aqua — The site continues to pour concrete sides (framing) of balconies and their waterproofing, installation of gypsum cardboard frame, installation of…
Family Club — Ceramoblock walls continue to be laid in blocks A and B. The floor slab formwork in block B is also being assembled.
Villas — Waterproofing of villas and foundations is ongoing. The foundations are also undergoing formwork removal and laying of sewer lines.
Riviera — Fireplaces are being installed in Block A. In block B - laying of ceramic block walls. In blocks A and B, staircases are being installed, and in block…
Facade works continue, porcelain stoneware is being laid in the mockup, painting works on the first floor are underway, and fire pipes, drainage trays and…
Family Club — Ceramoblock walls continue to be laid in blocks A and B. The floor slab formwork in block B is also being assembled.
Aqua — The site continues to pour concrete sides (framing) of balconies and their waterproofing, installation of gypsum cardboard frame, installation of…
Villas — Waterproofing of villas and foundations is ongoing. Formwork is also being dismantled in the foundations and sewer lines are being laid. Crushed stone…
Aqua — Ceramoblock walls are being laid on the 20th floor. Concrete sides (frames) of balconies are being poured and balconies are being waterproofed. A…
Riviera — In Block A the fireplaces are being installed, in Block B the ceramic block walls are being laid and the floor slab formwork is being dismantled, in…
Facade works are underway, porcelain stoneware is being laid in the mockup, painting works on the first floor are underway, and fire pipes, gutters and…
Family Club — Ceramoblock walls continue to be laid in Blocks A and B. In addition, the formwork for the floor slab is being assembled in Block B.
Villas — Work continues on waterproofing of villas and foundations, dismantling of foundation formwork, and laying of sewer lines in the foundations. Crushed…
Riviera — Daytime works in Blocks A and E - construction of fireplaces (A) and technological openings in the roof (E). In Block B, ceramic block walls are being…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st