Aqua — Reinforced concrete balcony curbs are being framed, balconies are being waterproofed, ceilings are being dusted, gypsum cardboard framework of internal…
Construction progress, complex updates and real estate investment news from Batumi
Aqua — Reinforced concrete balcony curbs are being framed, balconies are being waterproofed, ceilings are being dusted, gypsum cardboard framework of internal…
Air-conditioning routes are being installed. Facade works are in progress: installation of decorative elements of the northern facade, finishing of facades on…
Villas — The formwork of the sub-concrete layer and waterproofing of the villa foundations is being installed.
Riviera — In blocks A and B the formwork for staircases is being assembled. Laying of ceramic block in block B on the second floor is in progress. In block C…
Family Club — Ceramoblock walls continue to be laid in Block A, on the fourth and fifth floors. Reinforcement of the floor slab is underway in Block B.
Aqua — The site is being waterproofed and the territory is being cleaned. Ceramoblock walls are being laid on the 20th floor.
Riviera — Internal staircases are being installed in blocks A and B (second and third floors). Ceramic block laying of external and internal walls in Block A on…
Plasterboard ceilings and air conditioning routes are being installed. Preparation of wall leveling works is underway. Geodetic layout for the railing is being…
Family Club — Laying of ceramic block walls in Block A, on the fourth and fifth floors, as well as cutting of reinforcement from concrete structures is in…
Aqua — Pouring of reinforced concrete sides (frames) of balconies and their waterproofing, installation of gypsum cardboard framework of internal partitions…
Riviera — In block A, drilling of technological holes is in progress. In Block B, fireplaces are being installed and ceramic block is being laid. In both blocks…
Facade works, installation of air-conditioning routes and decorative elements of the facade continue. Plasterboard ceilings are being installed. The pumping…
Family Club — Ceramoblock walls continue to be laid in blocks A and B. Floor slab formwork is being installed in block B, on the fifth floor, as well as floor…
Aqua — Pouring of concrete sides (frames) of balconies and their waterproofing, installation of gypsum cardboard frame of internal partitions, drilling of…
Villas — Insulation of the basement of villas, dismantling of formwork and compaction of backfill of foundations, vertical leveling of the site are being…
Riviera — In block A, drilling of technological holes is in progress. In Block B, fireplaces are being installed and ceramic block is being laid. In both blocks…
Facade works, installation of sub-sockets, air-conditioning routes, decorative elements of the facade continue. Metal balcony railings and plasterboard ceilings…
Family Club — Ceramoblock walls continue to be laid in blocks A and B. Floor slab formwork is being installed in block B, on the fifth floor, as well as floor…
Aqua — The facility continues to pour concrete sides (frames) of balconies and their waterproofing, installation of gypsum cardboard framework of internal…
Villas — Insulation of the basement of villas, installation of formwork, concreting and compaction of backfill of foundations are carried out.
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st