Riviera — Block B: installation of slab formwork and laying of ceramic block on the 1st floor. Block E: installation of staircase reinforcement frame.
Construction progress, complex updates and real estate investment news from Batumi
Riviera — Block B: installation of slab formwork and laying of ceramic block on the 1st floor. Block E: installation of staircase reinforcement frame.
Aqua — On the 1st construction (Ground Floor) floor the block masonry and wall jointing with minwool and cement-sand mixture are in progress. Framing of…
Painting works are being carried out in the mocap and on the 4th construction (3 residential) floor. Facade works, installation of apartment electric boards…
Villas — Concreting of the foundation and sub-concrete layer has been carried out. The waterproofing of the villa foundations is in progress, as well as ballast…
Family Club — Improvement of the area between blocks A and B is in progress. Block A: laying of ceramic block walls. Block B: reinforcement of vertical…
Riviera — Block B: Ceramoblock walls are being built. Block C: installation of formwork for vertical structures is in progress. Block E: installation of…
Aqua — On the 7th (6 separate) and 8th (7) floors, the laying of ceramic block walls has begun. Balcony framing and dusting of ceilings in common areas is also…
Painting works in mocap, on 2 construction (1 residential) and 3 (2) floors are in progress. Facade works, installation of apartment electrical panels, screed…
Villas — The waterproofing of villa foundations, installation and reinforcement of foundation formwork, as well as dismantling the formwork of the complex…
Family Club — Block A: construction of ceramic block walls is in progress. Block B: dismantling of the floor slab formwork started
Riviera — Block B: vertical structures are concreted, ceramic block walls are being laid Block C: vertical structures are being reinforced and formwork is being…
Aqua — Ceramoblock walls are being laid on the 1st construction (Ground Floor) floor. Balcony framing and dusting of ceilings in common areas is in progress…
Painting works are in progress in the mocap, on 2 construction (1 residential) and 3 (2) floors. Facade works, installation of apartment electrical panels…
Villas — Waterproofing of villa foundations, installation and reinforcement of foundation formwork, as well as dismantling of the fence formwork of the complex…
Family Club — Block A: Ceramoblock walls continue to be laid. Block B: concreting of vertical structures was carried out.
Riviera — Block E: installation of staircase formwork is in progress. Block B: construction of ceramic block walls and reinforcement of vertical structures is…
Aqua — Ceramoblock walls are being laid on the 1st construction floor (Ground Floor). Dusting of ceilings in common areas and installation of stained glass…
Installation of heating systems, cold/hot water supply and GKL frames in common areas is in progress. Painting works on the mocap and on 2 construction (1…
Work is not underway due to weather conditions.
Family Club — On the 2nd floor of block A the masonry of balconies continues. In Block B, no work is being carried out due to weather conditions.
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st