Due to the storm warning, no external works are in progress. In Block E: installation of staircase formwork continues.
Construction progress, complex updates and real estate investment news from Batumi
Due to the storm warning, no external works are in progress. In Block E: installation of staircase formwork continues.
Aqua — On the 1st construction (Ground Floor) floor the walls are being laid with ceramic block. Balcony framing is in progress. Dusting of ceilings in common…
Installation of heating systems, cold/hot water supply, low-current fire extinguishing system and GKL frames in common areas is in progress. The masonry of…
Villas — Reinforcement of villa foundations and installation of foundation formwork is in progress. The fence of the complex is being laid.
On the 2nd floor of block A the masonry of balconies is in progress. Preparation for concreting of vertical structures was carried out in Block B.
Block B: concreting of vertical structures. Block E: formwork erection and concreting of staircases, wall masonry with ceramic block.
Aqua — The first batch of stained glass windows is being unloaded on the territory. On the 1st construction (Ground Floor) floor the walls are being laid with…
Villas — Concreting has been carried out and masonry of the complex fence has been started. Dismantling of foundation formwork continues
Riviera — Block B: installation of formwork and reinforcement of vertical structures is in progress Block E: ceramic block walls and staircase formwork…
Aqua — On the 1st construction (Ground Floor) floor the walls are being laid with ceramic block. Balcony framing works continue on the floors.
Installation of heating systems, cold/hot water supply, low-current fire extinguishing system and GKL frames in common areas is in progress. The masonry of…
The masonry of the elevator shaft portals, installation of the framework for plasterboard lining of stairwells continues. On the 2nd construction (1…
In Block A, ceramic block masonry walls continue to be laid. Reinforcement of vertical structures is in progress in Block B.
Block B - excavation works, ceramic block walling and column formwork installation are in progress. Block E - installation of staircase formwork is in progress.
Ceramic block walling continues on the 1st construction (Ground Floor) floor. On the 13th construction (12 hotel) floor electrical installation works in mocap…
Installation of low-current fire extinguishing system, cold/hot water supply and heating systems is in progress. Elevator portals are being laid, GKL-frames are…
Block B - reinforcement of vertical structures.
Reinforcement of vertical structures continues in Block B. Ceramoblock walls are being laid in Block E.
Balcony framing continues on the floors. Wall masonry with ceramic block is going on the 1st construction (Ground Floor) floor. Mocap installation works are…
Installation works are in progress: cold/hot water supply systems, heating systems, water supply meters, low-current fire extinguishing system, GKL frames for…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st