Villas — Reinforcement and concreting of villa foundations has been carried out. The installation of formwork for the fence of the complex is in progress.
Construction progress, complex updates and real estate investment news from Batumi
Villas — Reinforcement and concreting of villa foundations has been carried out. The installation of formwork for the fence of the complex is in progress.
Family Club — On the 3rd floor of the block A continues laying of walls with ceramic block.On the 4th floor of the block B is reinforcing of vertical…
Riviera — Reinforcement of vertical structures and excavation works continue in Block B. Installation of staircase formwork and laying of ceramic block walls is…
On the 1st construction (Ground Floor) floor, the masonry walls are being laid with ceramic block. Installation of mocap is going on the 13th (12th) floor…
The installation of cold and hot water supply and heating systems, as well as the laying of elevator portals made of gas-silicate block is in progress…
Villas — Works on reinforcement and installation of foundation formwork are in progress, as well as the installation of formwork for the fence of the complex.
In Block A, ceramic block walls are being laid on the 3rd floor. Reinforcement of vertical structures continues in Block B.
Riviera — Concreting of the floor slab has taken place in Block B. Installation of stairway formwork and ceramic block wall masonry continues in Block E.
Ceramic block walls are being laid on the 1st construction (Ground Floor) floor. The mocap installation is continuing on the 13th (12th) floor. Balcony framing…
Concreting of the site for the installation of the passenger and freight hoist has been carried out on the territory. On the 1st construction (Ground Floor)…
Installation of heating and cold/hot water supply systems, masonry of elevator portals with gas-silicate block, tank connections are in progress. Painting works…
Villas — Reinforcement of the foundations continues, as well as installation of foundation formwork and fencing of the complex.
Block A Ceramoblock walls on the 3rd floor and dismantling of elevator shaft formwork. Block B Reinforcement of vertical structures.
Riviera — The following works are in progress in Block E: - installation of staircase formwork - laying of ceramoblock walls - installation of technological…
Work is underway to connect the tanks, waterproof the terraces, and install GKL frames at the storm drain frames and in the common areas. Installation of…
Villas — They are assembling the formwork for the fence of the complex, the formwork for the foundations of the villas, as well as reinforcing the foundations.
On the 3rd floor of block A the walls are being laid with ceramic block. On the 4th floor of block B - reinforcement of vertical structures.
Block C - construction of drainage system. Block B - reinforcement of the floor slab. Block E - installation of staircase formwork, laying of ceramic block…
Aqua — Ceramic block walls are being laid on the 1st construction (Ground Floor) floor. The installation of GKL frames and balcony framing is in progress. On…
Work on waterproofing of terraces has started. Installation of GKL-framework in the framing of storm drains and common areas, heating, cold/hot water supply…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st