Aqua — On the 6th construction (5) hotel the installation of technological openings and monolithic sides of balcony framing is in progress.
Construction progress, complex updates and real estate investment news from Batumi
Aqua — On the 6th construction (5) hotel the installation of technological openings and monolithic sides of balcony framing is in progress.
Outside, facade works and roofing are in progress. Plastering of walls continues on the floors.
Ceramic block walls are being laid on the 2nd floor of Block A.
On the 2nd floor of Block A, ceramic block walling continues. In Block B, the formwork for the 2nd floor columns is being assembled. In Block C, the…
Aqua — On 7 construction (6 hotel) technological holes are being made. On 5 (4) monolithic sides of balcony framing are being installed.
Facade works continue on the outside, while inside the walls are being plastered and hot and cold water supply systems are being installed.
Block A - on the 2nd floor the walls are being laid with ceramic block.
Block A - the walls are being laid with ceramic block on the 2nd floor. Block B - installation of column formwork and floor slab is in progress.
Aqua — Installation of formwork, reinforcement and concreting of balcony framing boards is performed on the 5th construction (4 hotel) floor.
Plastering works are underway on the floors, as well as installation of hot and cold water supply systems.
Block A - on the 2nd floor the walls are being laid with ceramic block. Block B - the floor slab formwork is being installed on the 3rd floor.
Aqua — Installation of technological openings has been started on the 8th construction (7 hotel) floor, the monolithic sides of balcony framing are being…
Outside, facade works and connection of gas supply systems are in progress. Inside, plastering of walls and installation of hot and cold water supply systems is…
On the 1st and 2nd floors of Block A, wall masonry with ceramic block continues. Reinforcement of the floor slab is in progress on the 3rd floor of Block B.
Block A - on the 2nd floor the walls are being laid with ceramic block. Block B - reinforcement of columns. Block C - preparation for column reinforcement.
Aqua — On the 5th construction (4 hotel) floor, formwork installation, reinforcement and concreting of balcony framing boards are in progress. On the 9th (8)…
Facade and plastering works, installation of installations in bathrooms are in progress. Installation of hot and cold water supply systems has started.
Reinforcement and formwork installation of vertical structures continues on the roof in Block A. Ceramic block wall masonry is in progress on the 2nd floor…
Wall masonry with ceramic block continues on the 2nd floor of Block A. Reinforcement of vertical structures is underway in Block B. Preparation for…
Aqua — Technological openings are being made on the 9th construction (8 hotel) floor. Installation of monolithic sides of balcony framing is carried out on the…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st