07.09.2024 — Elite Family Residence

Real estatePublished Updated 1 min read0 views
Share:Link copied
07.09.2024 — Elite Family Residence

07.09.2024 — Elite Family Residence — Finishing of the north, south and west façade continues at the site. Preparation of the lift shaft (work of a climber), connection of the water supply system, installation of reducers, installation of metal railings and pressure regulators, strapping of the fire pump, grouting of a trial section of floor tiles. Wall finishing is in progress in the mockup.