12.08.2024 — Wyndham Grand Residences Batumi Gonio. Riviera — The bulk of the day's work is in blocks B, C and D: dismantling of formwork of vertical structures and floor slab, construction of ceramic block walls, installation of internal stairs.
12.08.2024 — Wyndham Grand Residences Batumi Gonio. Riviera — The bulk of the day's work is in blocks B, C and D: dismantling of formwork of vertical structures and floor slab, construction of ceramic block walls, installation of internal stairs.