14.09.2024 — Elite Family Residence

Real estatePublished Updated 1 min read0 views
Share:Link copied
14.09.2024 — Elite Family Residence

14.09.2024 — Elite Family Residence — Facade finishing, installation of metal railings, waterproofing of fire tanks, and trial tile installation continue at the site. On the ground floor the walls are being finished. On the first floor - installation of plasterboard rails for ceilings. On the third and fourth floors - electrical installation works (wiring, continuity testing).