Get a Consultation
Georgian
עברית

← All news

14.09.2024 — Elite Family Residence

ProjectsPublished Updated 1 min read
Share:Link copied
14.09.2024 — Elite Family Residence

14.09.2024 — Elite Family Residence — Facade finishing, installation of metal railings, waterproofing of fire tanks, and trial tile installation continue at the site. On the ground floor the walls are being finished. On the first floor - installation of plasterboard rails for ceilings. On the third and fourth floors - electrical installation works (wiring, continuity testing).

Wyndham Grand Batumi Gonio Editorial

Author

Blog editorial team

We write about the Batumi and Georgia real estate market, hotel room investments and the construction progress of the complex.

All posts by the author →

More news