19.08.2024 — Elite Family Residence — Facade works, installation of fire extinguishing system pipes, air conditioning mains, drainage trays and sockets are in progress. Painting works are underway on the first floor. Plasterboard frame of the bathroom is being installed. Decorative facade elements have been delivered to the object, their installation has started.