20.08.2024 — Elite Family Residence — Facade works, installation and painting of fire extinguishing system pipes, air conditioning mains, drainage trays and sub-sockets are in progress. Painting works are underway on the first floor. The plasterboard frame of the bathroom is being installed. Installation of decorative elements of the facade is also underway.