24.08.2024 — Wyndham Grand Residences Batumi Gonio.

Real estatePublished Updated 1 min read0 views
Share:Link copied
24.08.2024 — Wyndham Grand Residences Batumi Gonio.

24.08.2024 — Wyndham Grand Residences Batumi Gonio. Riviera — Internal staircases are being installed in blocks A and B (second and third floors). Ceramic block laying of external and internal walls in Block A on the second floor and in Block B on the first floor is in progress. In Block C, the columns on the second floor are being installed. The floor slabs of the infrastructure building are being reinforced.