Elite Family Residence — 1. Diamond drilling for engineering openings. Layout and drilling are underway, necessary for future hotel utility installations. 2. Mock-up construction. This enables visualization and testing of design and materials. Finishing works are ongoing. 3. Cladding ceramic granite in the bathrooms, units on the 1st -3rd residential floors. 4. Installation of the decorative elements, units on the 2nd floor. It creates a visually pleasing interior that aligns with the design specifications. 5. Facade works. The decorative elements are being installed to create a visually appealing and protected exterior for the building. 6. Plastering in the bathrooms, 2nd -4th floors. The following activities continue: the installation of steel railings, the waterproofing of the balconies on the 4th and 5th floors, and terraces, electrical works.