fbpx

Elite Family Residence

1. Finishing Work.
— Painting works in units, 2nd, 5th floor.
— Laying of porcelain tiles on balconies and terraces.
— Facing of vestibules with travertine.

2. Waterproofing works.
On balconies.

3. Installation of platbands of entrance doors.

4. Improvement of the territory, infrastructure.
— Stone facing of the retaining wall.
— Monolithic works — waterfall device.