Elite Family Residence
1. Finishing works.
— Painting, the 1st, 3rd, 5th floors.
— Laying of porcelain stoneware on elevator portals.
— Laying of porcelain stoneware in units.
— Laying marble on staircases.
2. Facade works.
— Facade cladding with natural stone.
3. Insulation.
On the terraces. Installation of reinforcing mesh.
4. Floor screeding.
On the terraces.
5. Installation of railings on the staircases.