Elite Family Residence — 1. Floor tiling, units on the 3rd residential floor Surface leveling and tile installation with adherence to joints and required standards to ensure durability and longevity of the flooring. 2. Mock-up construction This enables visualization and testing of design and materials. 3. Cladding ceramic granite in the bathrooms, units on the 2nd – 3rd residential floors 4. Installation of the decorative elements, units on the 2nd floor It creates a visually pleasing interior that aligns with the design specifications. 5. Marble cladding of stairways This involves base preparation and laying marble slabs with precise alignment and joint work. 6. Facade works The decorative elements are being installed to create a visually appealing and protected exterior for the building. 7. Plastering in the bathrooms, 3rd -4th floors The following works are underway: the drywall installation on 1st – 2nd floors, the electrical installations on the 5th floor.