Get a Consultation

← All news

Elite Family Residence

Elite Family Residence

Elite Family Residence — 1. Plumbing. 2. Installation of ceramic granite tiles on the balconies Continued ceramic granite tiling work. 3. Finishing works. - Finishing of penthouses, on the 5th floor. - Painting of the stairwells. - Puttying of walls and ceilings in units, 1st–4th floors. - Tiling in units, 1st–2nd floors. - Tile grouting on loggias, 3rd floor. - Marble flooring in penthouses. 4. Facade works. - Plastering of the balconies. - Decorative elements are being installed. 5. Electrical installation. 6. Installation of the smoke extraction system. - Installation of dampers. - Integration of firefighting and smoke extraction systems. 7. Cast-in works for the entrance group. Concreting of the entrance group of the back yard. 8. Installation of unit entrance doors. Going on. 9. Welding of elevator hinges.