Get a Consultation
Русский
Georgian
עברית

← All news

Monthly construction report

ProjectsPublished 2 min read
Share:Link copied
Monthly construction report

Monthly construction report
Wyndham Grand Batumi Gonio. Family Club
November 2025

In November 2025, work continued on the main areas of the Wyndham Grand Batumi Gonio complex construction sites: monolithic construction, facades, engineering networks, and interior finishing. Work was carried out simultaneously on several sites, which allowed us to maintain a high pace and steady progress towards the key stages of the project.
Block A
— Work is being carried out on the roof to install a PVC membrane and roof flashings.
— Work is underway on the terraces to install the upper waterproofing coating and the final layer of porcelain stoneware.
— Work continues on the balconies on floors 1–4 to tile the floors with porcelain stoneware.
— Facade work continues: installation of mineral wool on balconies and facades, plastering work outside balconies, reinforcement for decorative plaster application, reinforcement and plastering on mineral wool and XPS on facades and balconies, priming for decorative plaster.
— Work continues on the installation of clinker tiles on the facade and slopes.
— Decorative elements of the crowning cornice have been installed.
— Metal frames for decorative elements on the 1st floor have been manufactured and installed, and the frames are being clad.
— Cables are being laid for the installation of facade lighting.

Block B
— Work has been completed on the terraces on the 5th floor and balconies on the 2nd-4th floors: installation of lower waterproofing coating, laying of storm sewer pipes, installation of drains.
— Work is underway on cladding the ceilings with concrete panels on the balconies on the 2nd-4th floors.
— Metal frames for decorative elements on the 1st floor have been manufactured and installed, and cladding of the frames is underway.
— Facade work continues: installation of mineral wool (facade, balconies) and XPS (terraces), plastering, reinforcement for decorative plaster application, reinforcement for mineral wool and XPS.
— Installation of decorative elements of the crowning cornice has begun and is continuing.
— Work is underway on the installation of clinker tiles on the facade and slopes.
— Stone flashings are being installed on the windows and slopes are being constructed on the windows.

Wyndham Grand Batumi Gonio Editorial

Author

Blog editorial team

We write about the Batumi and Georgia real estate market, hotel room investments and the construction progress of the complex.

All posts by the author →

More news