Monthly Construction Report
Wyndham Grand Batumi Gonio. Villas
September 2025

In September 2025, work continued on the main areas of the Wyndham Grand Batumi Gonio complex construction sites: monolithic construction, facades, engineering networks, and interior finishing. Work was carried out simultaneously on several sites, which allowed us to maintain a high pace and steady progress towards the key stages of the project.

— Monolithic work
Monolithic work is underway on four villas. The reinforcement of columns and floor slabs has been completed. Work is in progress on the installation of monolithic staircases in five villas.
— Masonry work
Completion of masonry work on the exterior walls of the second floor using ceramic blocks on the last two villas.
— Stained glass glazing
Stained glass frames and double-glazed windows have been ordered and delivered. Work has begun on the installation of stained glass structures.
— Facade work
Work is underway on the installation of facade mineral wool.
— Engineering networks
Storm sewer risers have been installed in all villas.
— Interior wall plastering
Work is underway on plastering the interior walls of 5 villas.